List of capital improvement projects (CIP).
Status: Current project
Project Category: Transportation
Project Estimated Cost: $25,000
Install signage and striping on 105th Ave from Denney Rd to the north end of the street at the cul-de-sac that serves as wayfinding for the Fanno Creek Trail.
Jabra Khasho, 503-526-2221mailboxengineering@beavertonoregon.gov
FY18-19: 2-1-19 and 2-15-19: Held discussions with ODOT and THPRD about project responsibility, priority and scope. 2-28-19: City priority is for ODOT to use funding for ped/bike improvements on the Hall Blvd bridge over Hwy 217 rather than along 105th Ave.
Project is listed in the Neighborhood Bikeways Plan under Project 68.