CIP 8141 - SW 85th Ave – Ernst Rd Storm Project

Status: Current project

Project Category: Storm

Project Estimated Cost: $200,000

Project Description

Beaverton Operations and Maintenance staff have an urgent need to abandon an existing outfall and realign the storm drainage system. The existing outfall pipe is collapsing and has extremely poor access which makes maintenance and rehabilitation or replacement work difficult. The existing outfall pipe is a 10” concrete pipe, located between two houses, under a large tree, and outfalls onto steep ground. The ground downstream of the outfall has had significant erosion. The outfall pipe will be realigned to drain to another location nearby.

Project Manager(s)

Tristan Wear, 503-350-4059
mailboxengineering@beavertonoregon.gov

Project Schedule

FY23 - Analysis and Design
FY24 - Construction

Project Justification

The existing outfall pipe is collapsing and cannot be maintained or rehabilitated due to its location between houses, under trees, and on steep ground.