List of capital improvement projects (CIP).
Status: Completed project
Project Category: Storm
Project Estimated Cost: $560,000
This project will install catch basins at the intersection of SW 141st Ave. and SW Millikan Way to reduce the frequency of flooding at the intersection. Stormwater conveyance pipes will be installed as well as a pretreatment vault. The stormwater pretreatment vault will collect mud and debris that wash off the street and keep it out of the creek. The existing curb ramps at the intersection will be removed and replaced with ADA compliant curb ramps.
Mark BoguslawskiTamara Connolly, 503-350-4025Tristan Wear, 503-350-4059mailboxengineering@beavertonoregon.gov
FY15/16: Begin design by City staff. FY16/17: Continue design by consultant. FY17/18: Continue design by consultant. FY18/19: Complete design by consultant. FY19/20: Complete construction.
Project will address localized street flooding on Millikan Way that occurs several times each winter as well as provide pretreatment to surface water runoff prior to discharge into Beaverton Creek.