List of capital improvement projects (CIP).
Status: Current project
Project Category: Water
Project Estimated Cost: $690,000
Replace existing waterline with approximately 3400 feet of 6-inch, 8-inch, and 12-inch ductile iron pipe and associated hydrants, water, and fire services.
Aaron Lee, 503-526-2446mailboxengineering@beavertonoregon.gov
FY 19-20: Topographic survey in progressFY 20-21: Begin Preliminary design.
The existing water main is made of cast iron pipe and was constructed in 1975. This water main has experienced numerous breaks in recent years. Corrosive native soils have contributed to a much shorter useful life of the water pipe and fittings. Water Operations staff have rated this waterline a top priority replacement project.