List of capital improvement projects (CIP).
Project Category: Water
Project Estimated Cost: $330,000
Replace existing waterline with 1100 feet of 8-inch ductile iron pipe and associated hydrants and water services.
Aaron Lee, 503-526-2446mailboxengineering@beavertonoregon.gov
Feb 2018: Emerio Design completed topo.Jan 2019: Staff competed design.Mar 2019: Project advertised for bid.Aug 2019: Project Completed
The replacement of the existing waterline is needed due to age and condition and to improve fire protection in the area.