Status: Completed project
Project Category: Water
Project Estimated Cost: $4,250,000
Install an intertie with the Willamette Water Supply (WWSP) transmission pipe. Construction prior to WASHCO 209th Ave/234th Ave and TV Hwy Intersection Improvements project to avoid conflicting construction.
unassignedmailboxengineering@beavertonoregon.gov
FY17-18: Coordination with WWSP staff concerning project design. City staff to contribute to design as necessary. FY18-19: Complete design and bid the construction. FY19-21: Construction. Project delayed due to additional coordination with WWSP for design revisions to 16-inch turnout, first turnout constructed as part of WWSS.FY 21-22: Project closeout.
Installation of intertie connection with WWSP is necessary to provide redundancy to City water supply in case of emergency and add capacity to the system supply structure.