CIP 4139 - 114th Ave (Canyon Rd-McBride Pl) 12-inch Waterline Replacement

Status: Completed project

Project Category: Water

Project Estimated Cost: $246,000

Project Description

Replace 684 feet of existing 8-inch cast iron waterline with 12-inch ductile iron pipe and associated structures.

Project Manager(s)

unassigned
mailboxengineering@beavertonoregon.gov

Project Schedule

FY16-17: 8-17-16: Potholing completed. 8-22-16: W&H Pacific contract approved for engineering services. 8-24-16: 60% design completed. 9-7-16: 100% design completed. 9-9-16: Project advertised. 9-30-16: Bids opened. Trench Line Excavation is the lowest responsive bidder. 10-19-16: Precon. 10-11-16: Award contract. 11-14-16: Began construction. 12-2-16: Waterline work completed. 12-5-16: Paved 114th Ave. 3-20-2017: Paved Canyon Rd.

Project Justification

The replacement of the 8-inch waterline is needed due to age/condition and to prevent future dig-ups of the street pavement and base rock to be installed by the new Cracker Barrel/Marriott development.