List of capital improvement projects (CIP).
Status: Current project
Project Category: Water
Project Estimated Cost: $945,000
Construct 1,600 feet of 8-inch, 6-inch, & 4-inch waterline on SW 22nd St from SW Dale Ave - SW Hall Blvd.
Aaron Lee, 503-526-2446mailboxengineering@beavertonoregon.gov
FY 20-21: Begin DesignFY 20-21 Finalize DesignFY 22-23 Refresh Design, advertise for construction contract
The existing water main is made of cast iron pipe and was constructed in 1966. This water main has experienced numerous breaks in recent years. Corrosive native soils have contributed to a much shorter useful life of the water pipe and fittings. Water Operations staff have rated this waterline a top priority replacement project.