CIP 4135 - Griffith Dr 8-Inch Waterline

Status: Current project

Project Category: Water

Project Estimated Cost: $900,000

Project Description

Construct 3100 feet of 8-inch and 12-inch waterline along complete loop of Griffith Dr.

Project Manager(s)

Aaron Lee, 503-526-2446
mailboxengineering@beavertonoregon.gov

Project Schedule

FY 19-20: Consultant to begin design.
FY 20-21: Complete design and construction.
FY 21-22: Project closeout.

Project Justification

The existing water main is made of cast iron pipe and was constructed in 1976. This water main has experienced numerous breaks in recent years. Water Operations staff have rated this waterline a top priority replacement project.

Project Image(s)

CIP 4135 Project Map for SW Griffith Dr, bounded by Lombard Ave, Beaverton Hillsdale Hwy, Hwy 217 and 5th St.