List of capital improvement projects (CIP).
Status: Current project
Project Category: Water
Project Estimated Cost: $900,000
Construct 3100 feet of 8-inch and 12-inch waterline along complete loop of Griffith Dr.
Aaron Lee, 503-526-2446mailboxengineering@beavertonoregon.gov
FY 19-20: Consultant to begin design.FY 20-21: Complete design and construction.FY 21-22: Project closeout.
The existing water main is made of cast iron pipe and was constructed in 1976. This water main has experienced numerous breaks in recent years. Water Operations staff have rated this waterline a top priority replacement project.