CIP 4134A - PRV Improvements at 153rd Dr & Beaverton Creek TC and Division St & Village Pl

Status: Completed project

Project Category: Water

Project Estimated Cost: $350,000

Project Description

Construction of new pressure reducing valve (PRV) vaults that separate pressures zones.

Project Manager(s)

unassigned
mailboxengineering@beavertonoregon.gov

Project Schedule

FY17-18: Complete design and begin construction.
FY18-19: Complete construction.

Project Justification

In Dec 2016 City Council authorized the withdrawal of the remainder of Cedar Hills Crossing water service from Tualatin Valley Water District (TVWD). The 153rd Ave PRV is necessary to create a City water 435 pressure zone for the CE John development between Jenkins Rd and Walker Rd. The Division St & Village Pl PRV will add a connection to the 36-inch transmission line, improve fire protection, and allow for future water system improvements in the area. The PRVs will be remotely operated from a City water system computer.