CIP 4123 - Barlow Ct 6-Inch Waterline

Status: Completed project

Project Category: Water

Project Estimated Cost: $400,000

Project Description

Construct 1700 feet of 6-inch and 8-inch waterline from Barlow Rd to Barlow Rd.

Project Manager(s)

Aaron Lee, 503-526-2446
mailboxengineering@beavertonoregon.gov

Project Schedule

Design in progress

Project Justification

The existing water main is made of cast iron pipe and was constructed in 1967. This water main has experienced numerous breaks in recent years. Corrosive native soils have contributed to a much shorter useful life of the water pipe and fittings. Water Operations staff have rated this waterline a top priority replacement project.

Project Image(s)

CIP 4123 Project Map for SW Barlow Ct, north of Barlow Rd, between 144th Place and Wilson Ave.