List of capital improvement projects (CIP).
Status: Completed project
Project Category: Water
Project Estimated Cost: $1,350,000
Install roughly 1,200 feet of 16-inch DIP waterline from SW Siskin Ter to the South Cooper Mountain development area as shown along the alignment highlighted in blue below. Developers will then install the waterline from the end of the City project to SW 175th Ave. CIP 4122 will also install a pressure reducing valve and metering vaults.
unassignedmailboxengineering@beavertonoregon.gov
FY15-16: Began preliminary design and coordinated easement options with adjacent property owners. FY16-17: Completed ROW coordination. FY17/18: Began construction. FY18-19: Complete construction of waterline.
This project will strengthen the City's water service and provide redundancy to the South Cooper Mountain area and Mountainside High School. Additionally, the waterline extension and pressure reducing valves will provide a loop to the system which improves water quality and fire flow. This project is shown on the City's water master plan map.