CIP 4120 - Taralynn Ave (Allen Blvd - EOP) Waterline Replacement

Status: Current project

Project Category: Water

Project Estimated Cost: $400,000

Project Description

Replace 520 feet of 4-inch and 500 feet of 6-inch waterline with 6-inch and 8-inch ductile iron pipe from Allen Blvd to end of cul-de-sac.

Comments

The Waterline has been installed and now fully operational. Final site work is being completed as this waterline was built in conjunction with the Erickson Sewer Phase 1 project.

Project Manager(s)

unassigned
mailboxengineering@beavertonoregon.gov

Project Schedule

12-30-14: Design by staff is 50% complete.
FY 15-16: Continue design.
FY16-17: Project on hold due to groundwater contamination found near Allen Blvd and Taralynn Ave.
FY17-18: No work. FY18-19: No work.
FY 19-20: Project design finalized.
FY 20-21: Project to be constructed in conjunction with the Erickson Trunk Sewer Upsizing project (CIP 6006). Waterline has been installed and operational as of November 2020.
FY 21-22: Project Complete, Maintenance Period

Project Justification

The existing waterline has experienced numerous main breaks in the past few years. The old waterline is in need of replacement. Soil samples indicated the presence of iron-eating bacteria so zinc coated ductile iron pipe and copper services with zinc anodes are recommended as a replacement material. City Water Forces have rated this waterline a priority replacement project.

Project Image(s)

CIP 4120 Project Map for SW Taralynn Ave north of Allen Blvd, between Erickson and Main Avenues.