List of capital improvement projects (CIP).
Status: Completed project
Project Category: Water
Project Estimated Cost: $250,000
Replace 450 feet of 6-inch pipe and associated structures in in the Greenway Ridge Townhouses area. There are 20 units within the HOA.
unassignedmailboxengineering@beavertonoregon.gov
FY16-17: 12-14-16: Contract with CES to provide base map for Greenway Ridge Townhomes. Feb/Mar 2017: Potholing completed. 5-1-17: Greenway Ridge waterline replacement (CIP 4118) separated from CIP 4118A in order to insure that Greenway Ridge was completed in the summer of 2017. 6-9-17: Design for CIP 4118 completed. 6-21-17: CIP 4118 advertised. 6-28-17: CIP 4118 mandatory prebid meeting held. 8-14-17: Project began. 9-14-17: Project complete. 10-16-17: Punchlist complete.
Water main break in the winter of 2016 caused property damage within the Home Owners association area. Decision was made to replace the cast iron pipe.