List of capital improvement projects (CIP).
Status: Completed project
Project Category: Civic
Project Estimated Cost: $35,000,000
Construct an approx 74,000 square-foot building located on city-owned property at the corner of SW Hall Blvd and SW Allen Blvd. This location is where three patrol districts meet and is accessible by public transportation. Completion is expected to be in early 2020.
unassignedmailboxengineering@beavertonoregon.gov
FY17-18: The design and permitting phases of the project are underway and are expected to last 12 months. FY18-19: Complete design and permitting and begin construction. FY19-20: Continue construction. The construction phase of the project is anticipated to last 18 to 24 months.FY 20-21: Complete construction.
In November 2016, Beaverton voters approved a ballot measure to construct a modern, earthquake resistant police and emergency management building. The bond measure will not increase residents’ bond tax rate because it replaces the Beaverton City Library construction bonds.