List of capital improvement projects (CIP).
Status: Current project
Project Category: Transportation
Project Estimated Cost: $1,200,000
1. SW Allen Blvd – Implement an adaptive traffic signal system along SW Allen Blvd from SW Murray Blvd to SW Western Ave, install intersection illumination, and install reflectorized back plates to all existing signal heads. 2. SW Hall Blvd & SW Nimbus Ave - Replace two traffic signal poles to accommodate the northbound and southbound protected left turn signal displays, add intersection illumination, and install reflectorized back plates to all existing signal heads.3. SW Hall Blvd & SW Cedar Hills Blvd - Replace one traffic signal pole on the NW corner to a safe distance from traffic and add illumination.
Tina Nguyenmailboxengineering@beavertonoregon.gov
FY17-18: City Council approved and signed an Intergovernmental Agreement (IGA) with State of Oregon Department of Transportation (ODOT). The City paid the required 7.78% match for engineering. FY18-19: ODOT is now contracting for the required engineering services. FY19-20: ODOT prepares PS&EFY21-22 Bid Date March 2022FY22-23 Construction, Complete Project
The purpose of this project is to address some of the safety needs, congestion and delay issues within Beaverton.
CIP 3340 Transportation Project split map of SW Hall Boulevard &SW Nimbus Avenue, and SW Hall & SW Cedar Hills Blvd intersection project areas.