CIP 3340 - All Roads Transportation Safety (ARTS) Project for Systemic Signal & Illumination

Status: Current project

Project Category: Transportation

Project Estimated Cost: $1,200,000

Project Description

1. SW Allen Blvd – Implement an adaptive traffic signal system along SW Allen Blvd from SW Murray Blvd to SW Western Ave, install intersection illumination, and install reflectorized back plates to all existing signal heads.

2. SW Hall Blvd & SW Nimbus Ave - Replace two traffic signal poles to accommodate the northbound and southbound protected left turn signal displays, add intersection illumination, and install reflectorized back plates to all existing signal heads.

3. SW Hall Blvd & SW Cedar Hills Blvd - Replace one traffic signal pole on the NW corner to a safe distance from traffic and add illumination.

Project Manager(s)

Tina Nguyen
mailboxengineering@beavertonoregon.gov

Project Schedule

FY17-18: City Council approved and signed an Intergovernmental Agreement (IGA) with State of Oregon Department of Transportation (ODOT). The City paid the required 7.78% match for engineering.
FY18-19: ODOT is now contracting for the required engineering services.
FY19-20: ODOT prepares PS&E
FY21-22 Bid Date March 2022
FY22-23 Construction, Complete Project

Project Justification

The purpose of this project is to address some of the safety needs, congestion and delay issues within Beaverton.

Project Image(s)

CIP 3340 Transportation Project map of SW Allen Boulevard between SW Murray Boulevard and SW Western Avenue.


CIP 3340 Transportation Project split map of SW Hall Boulevard &SW Nimbus Avenue, and SW Hall & SW Cedar Hills Blvd intersection project areas.

CIP 3340 Transportation Project split map of SW Hall Boulevard &SW Nimbus Avenue, and SW Hall & SW Cedar Hills Blvd intersection project areas.